Workplan for Goal:
Oversight of District Operations
|
Prepared by: Julie Dobrow
Date: 9/21/05
|
|
Results to be achieved
|
- Ensure that District is “managed by a goals-plans-status review” process
- Timely review of key aspects of District operations
- Evaluate Superintendent against objective criteria
|
|
Relationship to other School Committee or District goals
|
- School Committee oversight of teaching, learning, curriculum development and professional development
(this goal also addresses aspects of managing District by goals)
|
|
Milestone events and dates
|
- Transportation review: revenue, schedule, satisfaction
9/15/05
- After-school Athletics review: revenue, enrollment, costs, financial aid
10/20/05
- LASMP review: revenue, enrollment, costs, financial aid
10/20/05
- Special Education program update
1/26/06
- Spending reviews
10/20/05
1/26/06
5/4/06
6/22/06
- Town Meeting Warrant item (capital and expense) status reviews
9/29/05
12/15/05(to coincide with voting the FY76 budget)
3/2/06
- District enrollment update
9/15/05
12/15/05 (to coincide with voting the FY07 budget)
6/1/06
- Review Hanscom facilities plan
9/15/05
10/26/05
1/26/06
6/22/06
- Review Lincoln facilities plans
10/6/05
12/1/05
6/22/06
other dates TBD
- Evaluate performance of Superintendent
1/26/06 distribute materials to SC members
3/16/06- discuss and adopt evaluation
- Review workplans for achieving district goals
-Review district project plans for academic year 9/29/05 and 10/6/05
-Review district workplans:
- Facilities 10/6/05
- Hanscom contract 10/6/05
-Review school improvement plans:
- Hanscom primary and middle- 10/6/05
- Status of Technology Planning 10/20/05
- Lincoln-10/20/05
- Evaluate progress of district and school based workplans
-Mid year review- 2/9/06
-End year review (Lincoln) 5/4/06, 6/1/06
(Hanscom) 5/18/06
- Hanscom contract
Establish subcommittee and review charge 9/29/05
Review workplan 10/6/05
Periodic reports TBD
- Adopt FY07 district goals
-Initial discussion: 5/18/06
-Second discussion: 6/1/06
-Adopt: 6/22/06
|
|
People and resources involved
|
- School Committee members
- Central office and school administrative teams
- No subcommittees directly involved in this workplan
|
|
Assessment criteria
|
- Ensure that District is “managed by a goals-plans-status review” process
-Were the workplans for district goals reviewed as scheduled?
-Were the mid-year and end-year status review of goals conducted as planned?
-Were the goals for FY07 discussed and adopted as planned?
- Timely review of key aspects of District operations
-Did the various milestone reviews described in this plan occur as scheduled and with appropriate content?
- Evaluate Superintendent against objective criteria
-Was a written evaluation presented at a public meeting, and was it objective, and did it follow criteria established in advance?
|